Portal de Totana

www.portaldetotana.com

Totana - SpanishTotana - English
detail of Totana

 

Replace a stretch of sewerage network in Rosa Street (01/08/2017)

The works, which cost more than 6,000 euros, consist of the replacement of 20 meters of Sanitation pipe that was practically undone, affecting dwellings in that area

The Department of Water and Sewerage has undertaken these days, as a matter of urgency, in a section of sewerage located at the height of 65 Rosa Street, consisting of the installation of 20 meters of pipe, which will prevent leaks in Houses and basements to have deteriorated the cement pipe whose age exceeds 50 years and was in bad condition, with a budget of 6,000 euros.

The lack of investment in Totana's Water and Sewerage networks in recent years has meant a serious deterioration in the sanitation networks that are very deteriorated and with serious problems of leaks in many streets of the population, according to the councilor of the Branch, Antonia Camacho.

"The problems that are not seen, seem to be less problems, but they are there and the leaks of sanitation are much more dangerous than those of water, because the pressure causes them to surface more quickly," said the mayor.

The lack of investment in water networks in recent years contrasts with the collection of more than one million euros in receipts for "investments."

An issue that must be clarified in the coming months to seriously address the investments needed to improve Water and Sewerage in Totana, Camacho said.

With little budget, staff and means, the Council continues to face the urgencies and needs pending the financial aid promised and approved in the regional budgets of 2017 by an amendment of the Parliamentary Group of Citizens, explained the councilor.

Despite having been working for several months with the technicians of the Directorate General for Water, the financial aid does not come to undertake an urgent task in the Water and Sewerage Service, necessary to raise the yield, economically improving the results and optimizing A service that is basic and would benefit if the measures taken for years were undertaken.

Source: Ayuntamiento de Totana

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Utilizamos cookies propias y de terceros para facilitar su navegación en la página web, conocer cómo interactúas con nosotros y recopilar datos estadísticos. Por favor, lee nuestra Política de Cookies para conocer con mayor detalle las cookies que usamos, su finalidad y como poder configurarlas o rechazarlas, si así lo considera.